| Client |
Scope of work |
Type of construction |
Value (£million) |
Contract period |
Year |
| Government |
Outer London DC |
Fit-Out |
10+ |
18 Months |
2007 |
| Service Provider |
Multiple Centres |
Fit-Out |
20+ |
9 Months |
2007 |
| Hosting Company |
New Data Centre |
Fit-Out |
34+ |
14 Months |
2007 |
| City Developer |
Bank Upgrade |
Rebuild |
5.8 |
15 Weeks |
2006 |
| Data Centre Developer |
St Just |
Rebuild |
9.5 |
38 Weeks |
2006 |
| Hosting Company |
Client Fit-Out |
Fit-Out |
1.3 |
15 Weeks |
2006 |
| Hardware Manufacturer |
Client Test Laboratory and Data Centre |
Fit-Out |
3.5 |
33 Weeks |
2006 |
| Satellite Television |
TV Studio |
New Build |
3.2 |
8 Months |
2005 |
| Telecommunications |
Infrastructure Upgrade |
Infrastructure |
1.3 |
3 Months |
2005 |
| Centriea |
Southern Data Centre |
Fit-Out |
14 |
11 Months |
2005 |
| UK Corporate |
South Data Centre |
Fit-Out |
14 |
11 Months |
2005 |
| Data Centre Developer |
London Data Centre |
Fit-Out and Plant Upgrade |
4.5 |
5 Months |
2005 |
| Satellite Television |
TV Studio |
New Build |
3.2 |
8 Months |
2005 |
| Spire Technology |
London Data Centre |
Fit-Out and Plant Upgrade |
4.5 |
5 Months |
2004 |
| Japanese Bank |
Mechanical Plant Upgrade |
Infrastructure |
1.5 |
6 Months |
2002 |
| KPN Qwest |
European Data Centre |
New Build Construction |
33 |
12 Months |
2002 |
| JPMC |
Power Infrastructure Upgrade |
Refurbishment |
5.1 |
7 Months |
2002 |
| US Bank |
Power Infrastructure Upgrade |
Refurbishment |
5.1 |
7 Months |
2002 |
| US Bank |
Data Centre & Dealing Space |
Fit-Out |
5.4 |
6 Months |
2001 |
| Hosting Company |
European Data Centre |
New Build |
33 |
12 Months |
2001 |